Day Shift — May 12, 2026
Floor Watch
Live operational status — items requiring attention
Shift OEE
78.4%
↑ 3.2% vs yesterday
Live — updates every 15 min
Machines Down
1
Mazak #2 — Alarm 138
At-Risk Jobs
2
1 high priority, 1 medium
Open NCRs
2
Awaiting disposition
Machines Running
7/9
77.8% utilization
Machine Status
Running Setup Down Idle
Haas VF-4 #1
Running
AP-7742 — Op 20
60%
complete
Haas VF-4 #2
Running
AP-5531 — Op 10
35%
complete
Haas VF-4 #3
In Setup
AP-3302 — Op 20 Setup
10%
complete
Mazak QTN #1
Running
AP-9914 — Op 30
50%
complete
Mazak QTN #2
Down — Alarm 138
AP-6678 blocked — Est. 2hr fix
action req.
Okuma LB #1
Running
AP-1144 — Op 40
90%
complete
Okuma LB #2
Running
AP-2267 — Op 20
40%
complete
Okuma LB #3
Running
AP-4421 — Op 10
20%
complete
Makino PS95
Running
AP-8831 — Op 10
55%
complete
At-Risk Jobs
2 flagged
AP-6678 Bearing Retainer
Mazak #2 down — Due May 11 (overdue)
HIGH Machine blocked — 2hr est. fix
AP-3302 Valve Body
Haas #3 in setup — Due May 12 (today)
MEDIUM Setup must complete by 10am
AP-7742 Hydraulic Manifold
Haas #1 running — Due Today EOD
WATCH 2 ops remaining, tight timeline
Open NCRs
2 open
NCR-2041 AP-9914 Spindle Housing
Bore diameter out of tolerance — Op 30
OPEN Raised May 11 — Qty: 3 pcs
NCR-2042 AP-5531 Valve Spool
Surface finish Ra exceeds spec — Op 10
OPEN Raised May 12 — Qty: 5 pcs
Shift Output Progress
68% of shift complete
Parts Completed Today 847 / 1,200 target
70% of daily target — on pace for completion
Jobs On Schedule 7 / 9 active jobs
78% on schedule — 2 flagged for review
Machine Utilization 77.8% 7 of 9 running
1 machine down, 1 in setup — target 85%+